NRJE Startup [ SNA NRJE User/Programmer Reference Manual ] MPE/iX 5.0 Documentation
SNA NRJE User/Programmer Reference Manual
NRJE Startup
Figure 2-4, later in this chapter, illustrates how to start and stop
NRJE. To start NRJE, you must do the following:
* Activate the data communications line and host PU and LUs.
* Start the SNA node using an MPE SNACONTROL START command.
* Start the NRJE workstation using an MPE NRJECONTROL START command or
an NRJE STARTWS command.
NOTE A job stream file must exist before you start a workstation.
An MPE job stream file is required to start each workstation. The job
stream starts NRJEMON, which is the father communication process for an
NRJE workstation. The structure of the job stream file and the STARTWS
command are described in the SNA NRJE Node Manager's Guide. SNACONTROL
START is described in the SNA Link Services Reference Manual or the SNA
Link/XL Node Manager's Guide. The MPE command NRJECONTROL START is also
described in the SNA NRJE Node Manager's Guide.
MPE/iX 5.0 Documentation